During PI Planning, one team discovers that another team must deliver an API first. Which artifact most directly helps the ART visualize that delivery timing and dependency?

AThe Measure and Grow assessment.
BThe ART planning board.
CThe Team Backlog.
DThe Iteration Retrospective notes.