A new team member asks when PI Planning happens and who leads it. Which answer matches SAFe?

AIt is typically a 2-day event every 8-12 weeks, led by the RTE, and held in the IP iteration.
BIt is a 1-hour daily event led by the Scrum Master during every iteration.
CIt is a monthly review led by Product Management after release.
DIt is an ad hoc meeting only when dependencies are already resolved.