Your team starts a new 2-week iteration tomorrow. Which description best fits Iteration Planning in SAFe?

AIt is a management review that replaces the daily stand-up for the whole PI.
BIt is the last event of the iteration, usually 2 days, where only engineers commit to PI goals.
CIt is the first event of the iteration, usually about 90 minutes, where team and business mutually commit to iteration goals.
DIt is a backlog cleanup ceremony led only by the RTE.