hard
Question 2 of 26

Two days before Iteration Planning, a stakeholder demands a guarantee that every item currently near the top of the Team Backlog will be delivered next iteration. What is the best SAFe response?

AExplain that refinement improves readiness, but actual commitment is made during Iteration Planning when the team and business agree on iteration goals.
BPromise all visible backlog items because the Product Owner already owns the backlog.
CEscalate to the RTE so the ART can force the team's commitment.
DRemove the items from the backlog so the question no longer applies.

Educational Content — CertQnA practice questions are written against official exam objectives, covering the same domains tested on the real exam. All content is original and independent — not actual exam questions, not affiliated with any certification vendor. Learn more about our content policy

Discussion

Be the first to share your understanding of this concept

⚠️ Discussion is for concept clarification only. Do not share or request actual exam questions or answers.

Sign in to join the discussion