Question 1 of 26

At the end of PI Planning, an ART wants evidence that teams aligned on delivery and dependencies. Which pair of outputs should they expect?

ATeam velocity charts and retrospective notes.
BCommitted PI objectives and an ART planning board.
CA portfolio roadmap and an organization chart.
DA release approval form and a defect log.