Forming Agile Teams as an Agile Release Train
medium
Question 7 of 32

A Product Owner tells stakeholders that everything currently visible in the Team Backlog is a firm promise for the next iteration. Which statement is more accurate in SAFe?

AThe Team Backlog is only a list of completed stories.
BThe Team Backlog can contain features but not stories or improvement work.
CThe Team Backlog is owned by the RTE, not the Product Owner.
DThe Team Backlog is a Kanban-based list of desired work managed by the Product Owner, not a set of commitments.

Educational Content — CertQnA practice questions are written against official exam objectives, covering the same domains tested on the real exam. All content is original and independent — not actual exam questions, not affiliated with any certification vendor. Learn more about our content policy

Discussion

Be the first to share your understanding of this concept

⚠️ Discussion is for concept clarification only. Do not share or request actual exam questions or answers.

Sign in to join the discussion