Forming Agile Teams as an Agile Release Train
medium
Question 5 of 32

Mid-iteration, a manager tries to reassign each developer's daily tasks. Under SAFe team operating norms, what is the better response?

AOnly the Scrum Master can choose who does each story.
BThe team self-manages how to meet the goal while staying aligned on commitments and priorities.
CThe manager should assign all tasks because self-management is limited to the Product Owner.
DTask assignment should wait until the next PI Planning event.