Forming Agile Teams as an Agile Release Train
easy
Question 4 of 32

A product grows beyond one team, and leadership wants to launch an ART. What size is most consistent with SAFe guidance?

AAbout 10-15 people with no need for Product Management or an RTE.
BAny size is equally preferred as long as the release date is fixed.
CAbout 200-300 people reporting through a single project manager.
DAbout 50-125 people aligned to a common vision and roadmap.