Question 2 of 36

Several teams on an ART have emerging dependency issues and a blocked external interface. Which event is the normal heartbeat for coordinating this and escalating cross-team impediments?

AART Sync.
BIteration Retrospective.
CInspect and Adapt.
DTeam Backlog Refinement.