A team says it will move faster if it postpones quality checks until the end of the PI. Which SAFe principle directly challenges that idea?

AQuality improves most when teams stop demonstrating work.
BQuality can be traded away when flow is more important.
CQuality is mainly the responsibility of Business Owners after release.
DQuality must be built in, not inspected in later.