RTE
Supporting PI Execution
hard
Question 5 of 26

An ART consistently misses its committed PI Objectives despite full sprints. Which RTE-led approach best fits SAFe?

AIncrease pressure on teams to commit to more.
BInspect ART-level flow, dependency density, refinement quality, and capacity allocation; bring patterns to I&A and adjust PI Planning practices accordingly.
CStop measuring PI Predictability.
DReassign team members across the ART without analysis.