Which is the right RTE action when ART Sync surfaces a cross-team dependency that emerged mid-PI?

ATell teams to handle it privately.
BCoordinate via Coach Sync and PO Sync, sequence work, ROAM the risk, and reflect updates on the ART planning board.
CReplace the dependent feature with a different one without analysis.
DDefer the dependency to the next PI silently.