Question 20 of 80

What effect do explicit WIP limits have on a Scrum Team's work?

AThey guarantee that throughput will increase every Sprint
BThey force a focus on finishing work and surface impediments and bottlenecks earlier
CThey replace the Sprint Goal as the team's primary commitment
DThey eliminate the need for a Definition of Done