easy
Question 8 of 80

How does the Kanban Guide for Scrum Teams define Kanban?

AA strategy for optimizing the flow of value through a process that uses a visual, WIP-limited pull system
BA software tool that visualizes a Scrum Team's Sprint Backlog
CA replacement for Scrum that eliminates time-boxed Sprints
DA method that requires the use of story points to plan work