In a pull system, when does the Scrum Team start a new work item?

AWhenever the Product Owner adds an item to the Product Backlog
BWhen capacity allows according to the WIP limits and policies in the Definition of Workflow
CAt the start of each day, regardless of WIP
DWhen a stakeholder requests it during the Sprint