What is the difference between the Definition of Workflow and the Sprint Backlog?

AThey are the same artifact under different names
BThe Definition of Workflow is the team's explicit way of working; the Sprint Backlog is the plan for the current Sprint
CThe Sprint Backlog defines workflow states; the Definition of Workflow lists the selected items
DOnly the Sprint Backlog includes WIP limits