A mature Scrum Team has progressively added stricter quality checks (security scans, performance budgets) to its Definition of Done. What is the most direct effect?

AVelocity will permanently increase
BSprint Planning becomes unnecessary because of automation
CThe Product Owner's accountability for value diminishes
DThe product's quality improves and undone work is less likely to be hidden