A Scrum Team is starting work on a brand-new product and the organization has no published quality standards. Who must create the Definition of Done?

AThe Product Owner, in consultation with stakeholders
BThe Scrum Master, drawing on industry standards
CThe Scrum Team itself, if none exists
DExternal architects assigned by management