A project uses a rate model and a requested period crosses two matching non-overlapping rate lines for the same criteria. What can happen?

AOne rate can apply to part of the period and another to the rest
BThe first matching rate line must cover the entire period
CThe request must fall back to the default rate card for the whole period
DThe same criteria can only have overlapping date ranges