A user's approved time card has no labor rate card matching that user and rate type. What rate is used?

AThe rate from the highest Order labor rate card
BNo rate is applied until a labor rate card is added
CThe default rate model for the project
DThe default hourly rate from com.snc.time_card.default_rate