During Team Sync, the team starts deeply solving an architectural problem and the event runs 45 minutes. What should the SM/TC do?

ALet the discussion continue because it is solving a real problem.
BRefocus to the 15-minute coordination intent and park the deep dive for a follow-up.
CCancel the next Team Sync because today's was long.
DReplace Team Sync with one-on-one coaching sessions.