hard
Question 2 of 56

An SM/TC notices the team's PI predictability is consistently far below 80% across multiple PIs. Which improvement focus best fits SAFe?

AIncrease iteration commitments to chase higher numbers.
BInvestigate planning quality, scope, dependencies, and capacity assumptions and address the root cause.
CStop tracking the predictability measure.
DMove all uncommitted work into stretch objectives.