A manager proposes that the Nexus Integration Team be the decision-maker for Product Backlog ordering. Is this correct?

ANo — the single Product Owner has final say on the contents and ordering of the Product Backlog
BYes — the NIT owns ordering on behalf of the teams
CYes, if the Product Owner is unavailable
DYes, but only for technical items