Question 3 of 16

A Scrum Master notices the team keeps turning the Iteration Review into an internal process discussion, leaving little time for stakeholders to inspect the increment. What should happen instead?

AMove the process discussion into the System Demo.
BHold a separate Iteration Retrospective focused on improvement, typically 60 minutes or less.
CWait until the end of the PI to talk about improvement.
DSkip stakeholder review and use only metrics.