In the identity services ART, the team receives a stable backlog of feature work before each iteration. Which team method is the better fit?

ASAFe Scrum, because the work has predictable arrival and benefits from iteration-based planning.
BSAFe Team Kanban, because every team must use flow-based work.
CNo team method until the ART stabilizes.
DPortfolio Kanban only.