Building high-performing teams
easy
Question 2 of 54

In the field-service scheduling ART, developers are receiving priority changes from several people. Who owns and prioritizes the Team Backlog?

AThe SM/TC.
BThe RTE.
CThe Product Owner.
DEach stakeholder separately.