Question 11 of 56

What three components make up Cost of Delay when calculating WSJF in SAFe?

AUser-Business Value, Time Criticality, Risk Reduction and/or Opportunity Enablement
BStory points, velocity, and capacity
CRevenue, cost, and headcount
DStrategic theme, vision, and roadmap