Facilitating PI Planning
medium
Question 5 of 20

Which is the right RTE action when team breakouts on Day 1 run long and risk losing draft plans?

ACut breakouts unilaterally.
BUse timeboxes, periodic checkpoints, and coach teams to produce draft plans with risks and dependencies on time, escalating systemic blockers.
CSkip the draft plan review.
DReplace breakouts with a written survey.