Question 9 of 40

Under which condition may a Sprint be cancelled, and who has the authority to do so?

ADevelopers may cancel when the work is too hard
BThe Scrum Master may cancel when the team is blocked
CThe Product Owner may cancel only if the Sprint Goal becomes obsolete
DStakeholders may cancel when priorities shift