If several Scrum Teams work on the same product, what should they share according to the Scrum Guide?

AThe same Product Goal, Product Backlog, and Product Owner
BThe same Sprint Backlog and Scrum Master only
CThe same specialists and reporting manager
DThe same release date and team charter only