Several stakeholders want a new backlog item added immediately. According to the Scrum Guide, what should they do?

AInsert it directly into the Sprint Backlog
BAsk the Scrum Master to overrule the Product Owner
CTry to convince the Product Owner
DVote as a committee and change the backlog