A Scrum Team adopts the Kanban practices described in the Kanban Guide for Scrum Teams. What happens to the Sprint?

AThe Sprint is replaced by continuous flow with no time-box
BThe Sprint remains time-boxed and continues to produce a Done Increment
CThe Sprint is extended indefinitely until WIP is empty
DThe Sprint is replaced by a Definition of Workflow