Mid-PI, the PO Sync surfaces that a planned Feature can no longer ship by PI end due to a vendor delay. Which response best fits SAFe?

AHide the delay from Business Owners.
BTransparently report status at PO Sync, re-plan affected scope with PM and POs, ROAM the new risk, and update PI Objectives or stretch as appropriate.
CLower iteration quality to make up time.
DCancel the PI.