Different members of a FinOps team are working on different phases at different cadences for the same environment. Which statement best matches official guidance?

AThis is incorrect because all personas must move through the phases together
BThis is normal because different members can work on different phases or at different cadence while examining the same technology use
CThis is allowed only in the Inform phase
DThis means the team skipped the lifecycle entirely