Release and Instance Strategy
hard
Question 2 of 16

After a non-production instance upgrade completes in ServiceNow Phase 5 guidance, which sequence best matches the documented next steps

ARun production UAT first, then create the project plan, then request a clone
BValidate the upgrade, install optional plugins, install custom apps and fix scripts, install update sets, then perform functional testing and monitor performance
CSkip validation and go directly to production if Development already passed
DCreate a clone profile, preserve database views, and postpone all testing until production

Educational Content — CertQnA practice questions are written against official exam objectives, covering the same domains tested on the real exam. All content is original and independent — not actual exam questions, not affiliated with any certification vendor. Learn more about our content policy

Discussion

Be the first to share your understanding of this concept

⚠️ Discussion is for concept clarification only. Do not share or request actual exam questions or answers.

Sign in to join the discussion