A project team is using a PERT chart to estimate the duration of an uncertain activity. The optimistic estimate is 3 days, the most likely estimate is 6 days, and the pessimistic estimate is 15 days. What is the PERT estimated duration?

A6 days
B7 days
C8 days
D9 days