A project manager is analyzing a scatter diagram produced during quality management and notices a strong positive correlation between the number of overtime hours worked and the defect rate in deliverables. What is the MOST appropriate action based on this finding?

AIgnore the correlation since causation has not been proven
BImmediately eliminate all overtime from the project
CInvestigate whether overtime is a contributing cause of defects and develop a targeted quality improvement response
DRemove the overtime data from the quality report

Educational Content — CertQnA practice questions are written against official exam objectives, covering the same domains tested on the real exam. All content is original and independent — not actual exam questions, not affiliated with any certification vendor. Learn more about our content policy

Discussion

Be the first to share your understanding of this concept

⚠️ Discussion is for concept clarification only. Do not share or request actual exam questions or answers.

Sign in to join the discussion