Skip to content
PK0-005
Project Management Concepts
easy
Question 3 of 34

Which risk response strategy involves eliminating the threat entirely by changing the project plan?

AMitigate
BTransfer
CAccept
DAvoid

Educational Content — CertQnA practice questions are written against official exam objectives, covering the same domains tested on the real exam. All content is original and independent — not actual exam questions, not affiliated with any certification vendor. Learn more about our content policy

Discussion

Be the first to share your understanding of this concept

⚠️ Discussion is for concept clarification only. Do not share or request actual exam questions or answers.

Sign in to join the discussion