A project team has completed all planned deliverables. The customer has reviewed them but has not yet provided formal written acceptance. What should the project manager do?

AProceed to close the project since deliverables are complete
BIssue a change request to extend the project
CObtain formal written acceptance of deliverables before proceeding to closure