Project Life Cycle Phases
hard
Question 2 of 30

An agile project team just completed its fourth sprint. During the sprint retrospective, the team identifies that the daily standup meetings are too long (averaging 30 minutes) and that team members are reporting non-impediment status updates. What is the BEST recommendation to improve the team's process?

ACancel daily standups and replace them with weekly status reports
BRefocus the standup to the three standard questions: What did I do yesterday? What will I do today? What impediments do I have?
CAsk the Scrum Master to provide a written status update instead
DExtend standups to 60 minutes to allow full discussion

Educational Content — CertQnA practice questions are written against official exam objectives, covering the same domains tested on the real exam. All content is original and independent — not actual exam questions, not affiliated with any certification vendor. Learn more about our content policy

Discussion

Be the first to share your understanding of this concept

⚠️ Discussion is for concept clarification only. Do not share or request actual exam questions or answers.

Sign in to join the discussion