A project is deploying a new application to production. The development team has been testing in a staging environment that mirrors production. Just before deployment, a critical defect is found in staging. What should the project manager do?

ADeploy to production on schedule since only the staging environment is affected
BDelay the production deployment until the defect is investigated, fixed, and re-tested in staging
CDelete the staging environment since it is causing confusion
DSkip the staging environment and deploy directly to production to save time

Educational Content — CertQnA practice questions are written against official exam objectives, covering the same domains tested on the real exam. All content is original and independent — not actual exam questions, not affiliated with any certification vendor. Learn more about our content policy

Discussion

Be the first to share your understanding of this concept

⚠️ Discussion is for concept clarification only. Do not share or request actual exam questions or answers.

Sign in to join the discussion