A project manager is evaluating the environmental, social, and governance (ESG) impact of a new data center construction project. The project will generate significant electronic waste during the decommissioning of legacy hardware. Which ESG consideration is MOST relevant, and what action should the project manager recommend?

ASocial: Provide job training programs for displaced workers
BGovernance: Ensure executive compensation is tied to project outcomes
CEnvironmental: Implement a certified e-waste recycling and responsible disposal program
DGovernance: Conduct an internal audit of the project budget

Educational Content — CertQnA practice questions are written against official exam objectives, covering the same domains tested on the real exam. All content is original and independent — not actual exam questions, not affiliated with any certification vendor. Learn more about our content policy

Discussion

Be the first to share your understanding of this concept

⚠️ Discussion is for concept clarification only. Do not share or request actual exam questions or answers.

Sign in to join the discussion