A fulfillment team completes order tasks linked to an SPM project. What synchronization does the Order Management integration perform?

AIt only copies the project short description into Order Management
BIt creates labor rate cards from the order tasks
CIt synchronizes project states between SPM and order line items, task and domain order states, and project task and order task states
DIt moves the project into Idea Portal for reassessment