A scenario is approved after date changes were tested. What is the effect on the planning items?

AOnly the scenario copy changes and live approved dates stay untouched
BThe updated scenario dates are recorded as the approved dates for the planning items
CAll items are removed from In Plan by default
DOnly dashboard widgets are updated